Homeowners and an electrician reviewing a solar plan outside a Perth home

Synergy and Western Power Solar Application Process in Perth

Quick answer: In Perth, a new solar system, a new battery or a change of inverter needs two approvals before any equipment goes on the wall: one from Synergy (your retailer) to export to the grid, and one from Western Power (the network operator) to connect to it. You apply to Synergy first and receive a Retailer Reference Number (RRN), then use that number in Western Power’s Embedded Generation Connection Application. Either you or your installer can submit both. After installation the system is registered with Western Power, your meter is changed if needed, and you wait for an approval to operate email before switching on.

This guide sets out the steps in order for a new system, for adding a battery and for upgrading an existing system, using the process published by Synergy and Western Power as at 20 November 2026. It is written for homeowners on the main South West grid (the SWIS) who want to know who does what and what the approval actually covers.

Who approves solar and batteries in Perth?

Two organisations are involved, and they approve different things. Synergy says you need to apply “to Synergy to export into the grid and Western Power to connect it to the grid”. Synergy handles your account, your buyback arrangement and, with Western Power, your metering. Western Power assesses whether the local network can take the system you want. Regional customers supplied by Horizon Power go through Horizon Power’s own process instead.

OrganisationRoleWhat it decides
SynergyElectricity retailer for most Perth homesIssues the Retailer Reference Number, confirms whether you qualify for the Distributed Energy Buyback Scheme (DEBS), arranges meter changes with Western Power
Western PowerNetwork operator (poles, wires and meters on the SWIS)Approves the inverter system for connection, sets the conditions of approval, registers the installed system, issues approval to operate
Your installerLicensed electrical contractorSite evaluation, system design, installation, commissioning and the Notice of Completion
Sources: Synergy, Distributed Energy System (DES) application process; Western Power, Inverter system up to 30kVA. Accessed 20 November 2026.

What are the steps to get a new solar system approved?

There are six steps, and installation is the fourth, not the first. The order below follows Synergy’s Distributed Energy System application process for systems under 30 kW and Western Power’s page for inverter systems up to 30 kVA.

StepWhat happensWho does it
1. Site evaluationThe site is assessed so the system suits the property and the right emergency solar management method is chosen, where that requirement applies.Your installer (Synergy recommends this happens before you apply)
2. Apply to SynergySynergy’s online DES application is completed. Synergy then issues a Retailer Reference Number (RRN).You or your installer
3. Apply to Western PowerThe Embedded Generation Connection Application is submitted with the RRN and the technical details of the system. Western Power sends a preliminary approval email.You or your installer
4. InstallOnce Western Power approves the application, the system can be installed according to the approved application.Your installer
5. Register the systemThe Embedded Generation Registration Form is submitted with the application reference number, the new inverter serial number and the circuit breaker rating (if required). This automatically triggers a meter service order if one is needed.You or your installer
6. Meter work and approval to operateWestern Power changes or reconfigures the meter if required and emails an approval to operate. Synergy notifies you that the application is complete.Western Power and Synergy
Sources: Synergy, DES application process (systems less than 30kW); Western Power, Inverter system up to 30kVA. Accessed 20 November 2026.

Systems above 30 kW follow a different path that starts with Western Power, so the steps above apply to typical homes only. For how these approvals fit around ordering, scheduling and install day, see our solar installation timeline for Perth.

Who submits the Synergy and Western Power applications?

Either you or your installer can submit them, and the homeowner remains responsible. Synergy states that “either you or your solar installer can complete the DES application form”. Western Power states that homeowners are responsible for connecting their inverter system to its network, and that you may authorise your solar system supplier to apply on your behalf. Its advice is to check with your supplier to confirm what actions you need to take.

So before you sign a contract, ask in writing who is lodging each application and who will complete the registration after install. If you live in a strata development or share a connection point, Western Power says you need to consult your strata company or management body before applying, because the generation capacity of a shared connection is split between every lot behind it.

What information do the applications need?

Western Power lists two things for its connection application: your RRN (which shows your emergency solar management control method, if applicable) and the technical details of your system, whether it is a new inverter, an upgraded inverter or an addition to an existing system. If the application goes to technical assessment, Western Power may also ask for a site diagram or a single line diagram.

For the registration step after installation, both Synergy and Western Power list the same three items:

  • the Embedded Generation Connection Application reference number
  • the new inverter serial number
  • the circuit breaker rating, if required.

Western Power also notes that the installer’s Notice of Completion can take at least three hours to appear on its system. If the installed inverter is a different make or model from the one in the preliminary approval, the inverter details can be updated in the registration form.

How long does approval take and what does it cost?

Most Western Power applications are decided quickly, and the application itself is free. Synergy does not publish an assessment timeframe for its part of the process.

ItemPublished timeframe or cost
Western Power connection application“Most applications are approved within an hour of submission.”
Applications needing technical assessmentAllow 15 business days
Share of applications reviewedWestern Power’s consumer guide says 85% are approved within 24 hours. 15% require review, and 70% of those are approved.
Meter change after registrationUp to 12 business days
Western Power application feeNo fee. Work may still be required so your connection meets Western Power’s standards.
Synergy chargesA one-off DEBS administration fee and, if your meter needs it, a meter upgrade or meter reprogram fee, added to your Synergy bill. Check Synergy’s application page for the current amounts.
Sources: Western Power, Inverter system up to 30kVA and Connecting your solar to the power grid; Synergy, DES application process. Accessed 20 November 2026.

Western Power’s consumer guide to connecting solar gives the most frequent reasons for declining a connection: the system exceeds the capacity of the overhead service cable, the system exceeds the capacity of the connection service, or the diagrams are invalid. If you have overhead power, Western Power’s top tip is a voltage rise assessment by an electrical contractor before the application goes in. A declined application is not the end. Western Power says it will explain the options, such as altering the proposed system or modifying the connection point, and a new application is then submitted.

What does the approval cover?

The approval covers a specific inverter system at a specific address, with conditions attached. It is not a general permission to install any solar or battery. Four things are tied to it.

Inverter capacity

Western Power’s standard application covers systems up to 30 kVA of total inverter capacity that meet its Basic Embedded Generator requirements. For Perth metro homes the generation limit is 15 kVA on a single-phase connection and 8 kVA per phase on three-phase. Solar and battery inverters both count towards the total.

Export limit

For systems installed or upgraded from 1 May 2026, export is limited to 1.5 kW unless you have an off-take agreement with your retailer, in which case the maximum in Perth metro is 5 kW. Western Power’s conditions of approval require installers to commission every system with a locally applied export limit of 1.5 kW. Any higher approved limit is then applied through metering or remote communications. Our guide to solar export limits in Perth explains the limits in full.

Emergency Solar Management

New and upgraded systems must be able to be remotely disconnected and reconnected in a grid emergency. Western Power says you nominate a control method for emergency solar management as part of the application where it applies, and the RRN displays that method. Under the rules that started on 1 May 2026, Energy Policy WA says all new systems must complete installation capability testing, and a household that prefers not to join an export product is held to the standard 1.5 kW export limit.

DEBS eligibility

Synergy’s application tells you whether you qualify for DEBS. Synergy describes DEBS as offered to residential, not-for-profit and educational customers who install or upgrade a system with an inverter capacity up to 5 kW that meets the emergency solar management requirements. DEBS pays 10c per kWh for exports between 3pm and 9pm and 2c per kWh at other times, on the first 50 kWh a day. If your design has more than 5 kW of inverter capacity, confirm with Synergy which buyback and export limit will apply before you commit. The rates and rules are covered in our Synergy DEBS feed-in tariff guide.

Do you need a new application to add a battery?

Yes, in most cases. Western Power says an Embedded Generation Connection application is required to “add another generation source such as batteries”, and Synergy treats battery installations as system upgrades that go through the same online DES form. The steps are the same six as for a new system: Synergy first, then Western Power, then installation and registration.

There is one exception on the Western Power side. You do not need a new Western Power application to add a battery module to an existing approved battery system, where the extra module connects only to the inverter already associated with that battery system and the inverter does not change. If you are weighing up the upgrade itself, see our guide to adding a battery to existing solar in Perth.

What approvals does a system upgrade need?

It depends on whether the inverter changes. Western Power’s rule turns on the inverter, while Synergy also wants to know about changes in system size.

ChangeNew Western Power application?
Installing a new solar or battery systemYes
Relocating an existing systemYes
Changing or replacing an inverter where the change is not like-for-likeYes
Changes that alter the approved inverter configurationYes
Like-for-like maintenance or replacement of an approved inverter or batteryNo
Adding or replacing panels with no inverter changeNo
Source: Western Power, Inverter system up to 30kVA (“You need Western Power approval if”). Accessed 20 November 2026.

Western Power defines like-for-like as equipment with the same maximum power rating, phase configuration and quantity as the existing approved system, and the replacement equipment must meet current approval requirements. It adds one specific warning: on a three-phase connection, replacing a single-phase inverter with an inverter greater than 3 kVA needs approval.

Separately, Synergy says that if you want to upgrade the size of your existing system you need to complete its DES application form, and that changing the capacity of your inverter also needs Western Power approval before any changes are made. So a panel-only upgrade can avoid a new Western Power application and still need to go to Synergy. Our guide to upgrading an old solar system in Perth covers the design side.

How does an upgrade affect an existing feed-in arrangement?

If you are on the older Renewable Energy Buyback Scheme (REBS), most upgrades move you to DEBS. Synergy lists three changes that require a REBS customer to apply for DEBS:

  • increasing the size of the renewable energy system
  • installing a home battery, or an electric vehicle set up to export to the grid
  • replacing the existing inverter with a new or different one, including a hybrid model.

REBS customers who make no change stay on REBS, subject to its terms and conditions. Synergy advises REBS customers who are upgrading or modifying a system to review those terms to see whether they can remain. Upgrades also bring the system under the current technical rules: Energy Policy WA says upgrades from 1 May 2026 must be capable of being remotely disconnected and reconnected, while an inverter replaced with a similar or exact model under warranty does not have to meet the new requirements.

Will your meter need to change?

Possibly. Western Power’s conditions of approval require the system to be connected through a Western Power approved import/export meter. Submitting the registration form automatically triggers a meter service order if one is required, which can be a meter replacement, a change of tariff or wiring in the inverter for the meter control method. Western Power says a meter change can take up to 12 business days.

Synergy says that if your meter cannot yet record exports the way DEBS needs, you may receive a Temporary Export Credit of 7.135 cents per unit, calculated on a net basis, until the meter is installed or reconfigured. Our guide to smart meters with Synergy and Western Power explains what the meter does once it is in.

What happens if you install without approval?

Western Power is clear that approval comes first: you need its approval before installing a new solar or battery system, and Synergy says your installer is permitted to install only once the connection application is approved. The published conditions of approval also set out what can go wrong afterwards:

  • the approval is void if the application details are later found to be invalid
  • the system must be installed as detailed in the approved application, including the diagrams
  • the system must not be connected after the expiry date recorded on the approval
  • all electrical work must be carried out by a licensed electrical contractor
  • Western Power may inspect the installation and may disconnect the equipment if it considers it a threat to safety, to quality of supply or to the network, or if it does not conform with the technical requirements.

A system that has been installed also should not be left running before the paperwork is finished. Western Power says the electrician may temporarily connect a system to test and commission it, and that the applicant receives an approval to operate email before the system is started. Neither Synergy nor Western Power publishes a specific penalty for unapproved systems on the pages we checked, so if you have bought a home with a system you are unsure about, ask Western Power to confirm what is approved at the address.

Getting your approvals sorted with Talk Energy

Talk Energy Solar & Battery has been installing in Perth for 7+ years, with 5,000+ installations completed by in-house SAA-accredited electricians under WA electrical contractor licence EC15564. The team can explain what your installation needs approved, whether that is a new solar system, a Sigenergy battery added to existing panels or an inverter change, and how the current Western Power limits apply to your connection.

To talk through your home, request a solar quote in Perth or call 08 6255 5914. We are at 16 Ogilvie Rd, Mount Pleasant WA 6153.

Frequently asked questions

Do I apply to Synergy or Western Power first for solar?

Synergy first. Synergy’s application produces a Retailer Reference Number (RRN), and Western Power requires that number in its Embedded Generation Connection Application. Western Power’s own guide says you or your installer need to apply to your retailer first, then to Western Power.

Can I submit the solar application myself or does my installer have to do it?

Either. Synergy says you or your solar installer can complete its Distributed Energy System application, and Western Power says homeowners are responsible for the connection but may authorise their solar system supplier to apply on their behalf. Confirm in writing who is lodging each form before installation is booked.

How long does Western Power take to approve a solar application?

Western Power says most applications are approved within an hour of submission, and that applications needing technical assessment should allow 15 business days. Its consumer guide puts it as 85% approved within 24 hours, with the remaining 15% going to review. A meter change after installation can take up to 12 business days.

Is there a fee for the Western Power embedded generation application?

No. Western Power states there is no fee for an Embedded Generation Connection Application, although work may be needed so your connection meets its standards. Synergy separately charges a one-off DEBS administration fee and a meter upgrade or reprogram fee where the meter needs changing.

Do I need approval to add more solar panels to my existing system?

Western Power says a new connection application is not needed for adding or replacing panels where there is no inverter change. Synergy still asks you to complete its Distributed Energy System application if you upgrade the size of your system, and REBS customers who increase their system size are required to apply for DEBS.

When can I turn my new solar system on?

After Western Power emails an approval to operate. The installer can temporarily connect the system to test and commission it, but the system is registered with Western Power first and any required meter work is completed before you start generating. Synergy also notifies you when the application is complete.